Daily Tracker for PWD’s Asphalt Crew

Date:

Nature of Work:

The asphalt crew will be cleaning storm drains.

When & Where:

July 23, 2024 (9:00 am) – July 23, 2024 (3:00 pm)

Canada Estate

Organizing Department:

Public Works Department, Wellington Road, Basseterre (869) 467-1122

Latest Articles

Related articles

Traffic Detour Between the Airport Slip Road and Shadwell Roundabout

The Public Works Department advises the general public of the following traffic detours at its project site along...

Public Works Department Assesses the Impact of Tropical Storm Ernesto as Normal Operations Resume

Basseterre, St. Kitts - One day after Tropical Storm Ernesto swept across the Leeward Islands, the Public Works...

PWD: Timeline for Clearing Debris and Bush at the South East Peninsula

Activity -The team will be clearing the road of debris and overhanging bushes. Drivers are asked to exercise...

PWD: Timeline for Demolishing and Casting Concrete Drains in Lower Monkey Hill

Activity -The crew completed the right side of the drain prior. They will focus on the left side.Time...