Each day, the Roads Team of the Public Works Department engages in various activities to maintain and improve public infrastructure all around the island. See what each crew that comprises the Roads Team is up to daily by tracking their locations and work activities.
  • PWD: Timeline for Constructing a Retaining Wall at Pump Bay, Sandy Point
  • 7/15/2024-9:0
  • 8/9/2024-15:0
  • Pump Bay, Sandy Point
  • https://mopieudt.gov.kn/wp-content/uploads/2024/07/concrete-cube-or-construction-brick-and-trowel-construction-concept-with-mason.jpg
  • July 25 & 26 - Casting of concrete flooring. July 29 - August 7 - Laying of blocks. August 8 & 9 - Backfilling and cleanup.
  • 0
  • PWD: Timeline for Clearing Debris and Bush at the South East Peninsula
  • 7/15/2024-9:0
  • 8/2/2024-15:0
  • South East Peninsula
  • The team will be clearing the road of debris and overhanging bushes. Drivers are asked to exercise caution when travelling through the area and to adhere to the road signs and instructions of our team.
  • 0
  • PWD: Timeline for Demolishing and Casting Concrete Drains in Lower Monkey Hill
  • 7/22/2024-9:0
  • 8/2/2024-15:0
  • Lower Monkey Hill, St. Peter's Parish
  • http://mopieudt.gov.kn/wp-content/uploads/2024/07/concrete-cube-or-construction-brick-and-trowel-construction-concept-with-mason.jpg
  • The crew completed the right side of the drain prior. They will focus on the left side.
  • 0
  • Daily Tracker for PWD's Asphalt Crew
  • 7/23/2024-9:0
  • 7/23/2024-15:0
  • Canada Estate
  • The asphalt crew will be cleaning storm drains.
  • Public Works Department, Wellington Road, Basseterre (869) 467-1122
  • 0
  • PWD: August Timeline for Constructing a Retaining Wall at Pump Bay, Sandy Point
  • 8/7/2024-9:0
  • 8/9/2024-15:0
  • Pump Bay, Sandy Point
  • http://mopieudt.gov.kn/wp-content/uploads/2024/08/Pump-Bay-2-August-2024.jpg
  • On August 7, the team will continue to lay blocks. From August 8 - 9, backfilling and cleanup will occur.
  • 0
  • PWD Begins Road Work Near Washington Archibald High School
  • 8/7/2024-9:0
  • 8/24/2024-15:0
  • About the Roadwork Schedule The schedule publishes the whereabouts of the roads team, the projects in which they engage, the duration of those projects and the nature of the work involved. Activities On Wednesday, August 7, 2024, the roads team engaged in preparations for road work in Taylors Village near the Washington Archibald High School. As the team works over the next few days, the Public Works Department asks the general public to exercise caution when travelling through the area. Date & Time August 7, 2024 (9:00 am) – To be released (3:00 pm) Location Taylors, Basseterre
  • 0
  • Conaree Cleanup
  • 8/26/2024-8:0
  • 8/30/2024-15:0
  • Conaree
  • The asphalt crew will be cutting trees in Conaree on the road leading to the Koi hotel. Please exercise caution when travelling through the area.
  • 0
  • Road Reinstatement in St. Peters
  • 8/26/2024-8:0
  • 8/30/2024-15:0
  • St. Peters
  • Concrete crew 1 will be in St. Peters reinstating the road. Please exercise caution when travelling through the area to protect yourself and our team.
  • 0
  • Drain Work
  • 8/26/2024-8:0
  • 8/30/2024-15:30
  • Verchilds
  • Concrete crew 2 will be working on drains in Verchilds. Please use caution when travelling through the area.